|
Recommendations and Guidelines
For The Installation and Operation of DPC JT and Refrigeration Units
DPC units are designed to be installed directly
on a stable surface. Good
quality soil fill should be used to build up to a non-flooding elevation.
A gravel, crushed concrete, or caliche cap should be considered
to stabilize the surface.
The skid should be relatively level to insure proper operation:
Two (2) inches maximum out of level along the long axis of
the skid, and one (1) inch across the width of the skid.
Do not allow the skid to be twisted by uneven support. This
may put the equipment and piping in a bind and create undue stress
on pressure retaining components.
The greatest weight is under the heat exchanger support beams,
and therefore the most benefit will be obtained by supporting these
beams from the pad.
Connecting
Piping
Connecting piping should be supported to keep loads on equipment
nozzles and skid connections to less than 200 pounds, each. DPC maintains inlet and outlet gas flange
connections on the same end of the skid to simplify unit size change
outs.
Inlet and Outlet Gas Connection Sizes:
Mini Skid 1 1/2 inch screwed
or socket welded
Model A 3 inch
600# ANSI raised face flange
Model B
4 inch 600# ANSI raised face flange
Model C
6 inch 600# ANSI raised face flange
Model D
6 inch 600# ANSI raised face flange
Liquid dump lines from all skids are one inch
screwed schedule 80 pipe.
Electrical
Classification
The process skid has a Class I Group D Division 1 Electrical Area
Classification due to the presence of instrument and power gas,
which vents continuously.
This must be considered when locating other electrical or
flame fired equipment in the area of the skid to ensure safe operations.
No smoking or any other open flames should be permitted in
the immediate vicinity of the unit.
THIS IS A HIGH PRESSURE NATURAL GAS CONDITIONING UNIT; THEREFORE
ALL APPROPRIATE INDUSTRY AND COMPANY SAFETY PRECAUTIONS AND STANDARDS
MUST BE ENFORCED.
Unit Performance, Instrumentation
and Controls
Performance of the unit to achieve the specified dew point of the
sales gas (cold separator temperature) is dependent on:
Inlet gas composition
Inlet gas temperature
Differential pressure across the JT valve
Proper operation of the JT unit equipment
Be advised that a JT unit is sensitive to inlet
gas temp. The performance guarantee for hydrocarbon dew point is
only valid up to the maximum inlet temperature given to DPC when
sizing the unit for the specific lease. If the inlet gas temperature rises above
the design temperature, the sales gas dew point specification may
not be achieved. Contact DPC if this occurs, or is anticipated
to occur for assistance in troubleshooting the installation.
The standard DPC JT unit is provided with a pressure controller to
set the JT valve to the required upstream pressure. If the transporting pipeline varies
widely in pressure, provision must be made to stabilize either the
differential pressure across the skid/JT valve, or to stabilize
the units outlet pressure.
DPC provides a hot gas bypass and valve on the JT unit to assist
in thawing the unit, or it can be used to reduce process temperature
temporarily until pressure control can be stabilized.
The DPC Mini JT unit was specifically engineered
to operate in the 200 to 1,000 MSCFD range. Due to the small size, DPC worked hard
to reduce the costs associated with this unit and thus the Mini
JT does not have the same instrumentation as the larger DPC units.
Contact DPC for assistance, if needed, on any of the above issues.
Lessee is expected to provide proper overpressure safety system protection
to prevent pressuring the DPC unit above 1440 psig.
DPC provides an inlet gas safety relief valve connection
for the Lessee’s use, if needed. The relief valve supplied by DPC is
only designed for thermal relief protection.
Inlet Moisture Considerations
Inlet gas moisture (water) content control is
required to maintain continuous operation of the gas conditioning
process. It is crucial that only a properly dehydrated inlet gas
be fed to the skid inlet to avoid ice and hydrate problems.
Dew Point Control recommends the following precautions to help prevent
hydrate and ice formation:
When operating at cold separator
temperatures of 35 degrees or higher:
Dehydrated gas fed to the DPC unit should have no more than
7#/MMSCF of water content.
Methanol injection is not normally needed with a properly operating
glycol unit.
When operating at cold separator
temperatures below 35 degrees:
Dehydrated gas fed to the DPC unit should have
no more than 3#/MMSCF water content, requiring, in most cases,
stripping gas on the re-concentrator reboiler, an eight tray contactor,
and a reboiler temperature of no less than 385 degrees.
Methanol injection is recommended to keep unit clear of hydrates
and ice when operating below 35 degrees.
When the unit chills the gas to the vicinity of hydrate formation
or ice formation temperature, methanol must be injected using the
DPC provided on-skid pump.
When using DPC’s high efficiency methanol injection system,
methanol flow should be set at 2.5 pounds of methanol per pound
of inlet water by setting the strokes per minute of the injection
pump. (1.2 gallons of methanol per MMSCF of
3# gas)
Because of the potential for a freeze blockage in the unit, it is
strongly recommended that a pressure controlled unit bypass be installed
across the inlet and outlet piping to permit continuous gas delivery
to the pipeline until skid operation can be restored to normal.
DPC will work with the Lessee to recommend or provide additional
controls and devices to meet specific or unique requirement for
any location.
Startup Assistance and Field Service
Standard DPC field service included in the rental
rate includes up to two days initial onsite startup assistance,
quarterly jobsite visits/consultations, and telephone and email
support for troubleshooting and assistance.
Additional onsite service is available on a Time and Material
reimbursement basis.
Operator
Maintenance Responsibilities
Lessee is expected to maintain the unit properly,
including safeguarding the inlet from various contaminants that
will materially interfere with the proper operation of the equipment. Lessee is required to properly
clean the unit at the end of the lease prior to returning it to
the DPC yard, otherwise a cleaning fee will be imposed.
As part of the DPC field service, DPC will coordinate with
lessee to inspect the unit prior to leaving the lease; this should
alleviate any additional cleaning fees.
DPC shall transfer to Lessee any warranties made to DPC by the manufacturer
or supplier. Specifically,
instrumentation items and chemical injection pumps will be repaired
and maintained during the initial 30 day operating period, while
the remaining equipment and piping will be repaired or rebuilt by
DPC during the entire term of the lease.
Normal and routine equipment and instrument maintenance,
such as cleaning, and clearing of debris from valves or other equipment,
or tightening of flange, threaded joint, or packing gland or stuffing
box leaks, will be the responsibility of the Lessee.
Operational Issues and Troubleshooting
Sales Gas Dew Point or Unit Freeze-up Problems
The biggest operational issue that DPC encounters with the operation
of JT units is the fluctuation of the sale pipeline operating pressures.
The DPC JT unit is instrumented to hold a constant pressure
upstream of the unit. When the sales pipeline varies in pressure,
this changes the differential pressure across the JT value, which
causes wide variations in the process temperatures. The
hydrocarbon dew point at the operating pressure of the unit is the
temperature of the cold separator.
Fluctuating temperatures will cause fluctuating dew point
temperatures. When
the process temperature gets too cold, the unit can freeze or hydrate. The simplest and most reliable fix for
varying pipeline pressure is to install a backpressure controller
and valve downstream of the unit.
Set this controller at approximately 30 psig above the highest
pressure swing expected on the pipeline.
This will stabilize both the pressure drop across the JT
valve the unit operating temperature.
The JT skid hot gas bypass valve (the one that has a manual regulator)
can also be automated with a temperature controller.
This gas bypass can control temperatures over a range of approximately
15 degrees. A thermowell is provided on the unit, on
the exchanger nozzle feeding gas to the separator, to permit field
installation of the temperature controller.
The manual hot gas bypass is used when icing or hydrate problems
are suspected. Opening
the bypass will warm up the unit approximately 15 degrees. This is an easy solution that does not
affect any instrument settings or operating pressures.
Pressure Storage and Facilities
Design and Procurement Statement
DPC offers, on a lease basis, pressurized storage
tanks, as a service to customers who lease DPC JT or refrigeration
natural gas conditioning equipment. The tanks are nominally 18,000 gallon, 250 psig rated ASME
pressure vessels, skid mounted, and suitable for truck tailgate
loading and unloading when completely empty.
This service is offered only to allow producers who are in
a schedule bind, time to find and provide their own tankage at a
more leisurely pace.
Pressure storage
tanks are leased under the following option:
Provision of a “bare” skid mounted pressurized
storage tank as described above, FOB our shop near Houston.
This is a straight non-service supported lease item, and
it is up to the lessee to provide installation, dress out of the
tank with appropriate and legal appurtenances (valves, including
reliefs, etc.) and to install per good engineering practice and
all rules and regulations of the appropriate authorities.
In addition, the lessee will need to install the correct
and appropriate truck loading facilities, including safety systems,
as required by federal, state and in some cases, local authorities.
These may include, but are not limited to: DOT, EPA, Texas
Railroad Commission, and State and Local Fire Marshals.
For dressing of the tank with appropriate devices and the
installation materials and labor required by the lessee’s Facility
Engineer or Contractor, we recommend the services of:
ProCon Construction, Inc
2875 Woods Road
Brookshire, Texas
77423
Contact: Royce Reid
Phone: (281) 375-6829
Fax:
(281) 375-5644
Email: rhreid@sbcglobal.net
Please note that Dew Point Control, LLC is not
set up or staffed to be a provider of facility or other engineering
services nor of material procurement assistance.
Advice and counsel are freely given as they relate to the
facilities that we lease, but facilities and site engineering should
be sought from appropriate companies in that business.
DPC will be glad to recommend such firms upon request.
Should
lessee elect to dress the tank(s) and provide installation materials
to it’s contractor and/or lease crews, DPC recommends that you contact
experts in the field of LPG storage and handling equipment who can
recommend and supply the correct material and installation advice,
such as:
Gas Equipment Company
11510 N. Petropark
Houston, Texas
77041
Contacts:
Jerry Drake, Jarrod Griffin
Phone:
(713) 896-1077
Fax:
(713) 896-9299
Email:
jdrake@gasequipment.com
or JGriffin@GasEquipment.com
|